In this example, ten parts that represent the expected range of the process variation were selected. Additionally, each part is fitted with one of two sub-components (a fixed factor), and you want to determine if this introduces part-to-part variability. Three operators measured the ten parts, four times per part (two times with each sub-component), in random order. You decide to conduct a gage R&R study (Expanded) to determine how much of your observed process variation is due to measurement system variation.
1 Open the worksheet GAGEGENERAL.MTW.
2 Choose Stat > Quality Tools > Gage Study > Gage R&R Study (Expanded).
3 In Part numbers, enter Part.
4 In Operators, enter Operator.
5 In Measurement data, enter Measurement.
6 In Additional factors, enter Subcomponent.
7 In Fixed factors, enter Subcomponent.
8 Click Terms. In Include terms in the model up through order, type 2.
9 Click Part-to-Part Variation. In Available terms, click Subcomponent to move it to Selected terms. Click OK twice.
10 Click Options. Under Process tolerance, choose Upper spec - Lower spec and type 8. Click OK.
11 Click Graphs. Under Plots of average measurements by two factors, enter Operator and Subcomponent. Do not change the defaults for the other graphs.
12 Click OK in each dialog box.
Session window output
Gage R&R Study: Measurement versus Part, Operator, Subcomponent
Factor Information
Factor Type Levels Values Part random 10 1, 2, 3, 4, 5, 6, 7, 8, 9, 10 Operator random 3 A, B, C Subcomponent fixed 2 A, B
ANOVA Table with All Terms
Source DF Seq SS Adj SS Adj MS F P Part 9 97.8123 97.8123 10.8680 173.10 0.000 x Operator 2 3.7413 3.7413 1.8706 10.03 0.038 x Subcomponent 1 1.7160 1.7160 1.7160 12.17 0.075 x Part*Operator 18 1.1493 1.1493 0.0638 3.29 0.000 Part*Subcomponent 9 0.1653 0.1653 0.0184 0.95 0.491 Operator*Subcomponent 2 0.2841 0.2841 0.1420 7.31 0.001 Repeatability 78 1.5158 1.5158 0.0194 Total 119 106.3841
x Not an exact F-test.
α to remove interaction term = 0.25
ANOVA Table with Terms Used for Gage R&R Calculations
Source DF Seq SS Adj SS Adj MS F P Part 9 97.8123 97.8123 10.8680 170.21 0.000 Operator 2 3.7413 3.7413 1.8706 10.03 0.038 x Subcomponent 1 1.7160 1.7160 1.7160 12.08 0.074 Part*Operator 18 1.1493 1.1493 0.0638 3.30 0.000 Operator*Subcomponent 2 0.2841 0.2841 0.1420 7.35 0.001 Repeatability 87 1.6811 1.6811 0.0193 Total 119 106.3841
x Not an exact F-test.
Variance Components
%Contribution Source VarComp (of VarComp) Total Gage R&R 0.078692 7.92 Repeatability 0.019323 1.95 Reproducibility 0.059369 5.98 Operator 0.042102 4.24 Part*Operator 0.011132 1.12 Operator*Subcomponent 0.006136 0.62 Part-To-Part 0.914649 92.08 Part 0.900349 90.64 Subcomponent 0.014300 1.44 Total Variation 0.993341 100.00
Process tolerance = 8
Gage Evaluation
Study Var %Study Var %Tolerance Source StdDev (SD) (6 × SD) (%SV) (SV/Toler) Total Gage R&R 0.280521 1.68313 28.15 21.04 Repeatability 0.139006 0.83404 13.95 10.43 Reproducibility 0.243658 1.46195 24.45 18.27 Operator 0.205188 1.23113 20.59 15.39 Part*Operator 0.105507 0.63304 10.59 7.91 Operator*Subcomponent 0.078330 0.46998 7.86 5.87 Part-To-Part 0.956373 5.73824 95.96 71.73 Part 0.948867 5.69320 95.20 71.17 Subcomponent 0.119583 0.71750 12.00 8.97 Total Variation 0.996665 5.97999 100.00 74.75
Number of Distinct Categories = 4 |
Graph window output
Gage R&R Study for Measurement